SASMO 2027 · Grades 4-5 · SET 011 · Self-study Question 3

SASMO · SASMO 2027 · Grades 4-5 · SET 011 · Self-study

Question 3

Team A can repair a road alone in 45 days. Working together, teams A and B complete $\frac{7}{12}$ of the work in 15 days. Team A then leaves for other projects. How many more days does B need to finish the road? Assume constant work rates.