Question 13
Tom must finish digging some foundations in 30 days. His own machine would take 50 days to do the whole job, and he wants to use it as much as possible. A larger machine that he can hire would finish the job in 21 days. Only one machine can work at a time. What is the least number of days for which he must hire the larger machine?