IKMC 2027 - Grades 9-10 - Self-study SET 2 - Thematic Batch 3 Question 16

IKMC · IKMC 2027 - Grades 9-10 - Self-study SET 2 - Thematic Batch 3

Question 16

Four workers begin a job intended to finish on schedule. After one day, two stop work because they are suspected of having SARS-CoV-2. The other two finish the job two days later than planned. All workers have equal, constant productivity. How many days was the job originally planned to take?

Question illustration
  1. 3 days
  2. 4 days
  3. 5 days
  4. 6 days
  5. 7 days