TIMO 2020 Grade 6 Heat Set 2 Question 5

TIMO · TIMO 2020 Grade 6 Heat Set 2

Question 5

Leo needs 18 days to finish a project. Bruce needs 21 days to finish the same project. If
Leo, Bruce and Mary do that project together, it takes 9 days. How many days does Mary
take to finish the project alone?