SASMO 2017 Primary 6 (Grade 6) Contest Question 8

SASMO · SASMO 2017 Primary 6 (Grade 6) Contest

Question 8

Ten workers take 2 days to dig a 5-metre well. How long will 4 workers take to dig a 10-metre well, assuming equal rates?

Question illustration
  1. 2 days
  2. 4 days
  3. 8 days
  4. 10 days
  5. None of the above