BBB 2021 - Grade 3 - Preliminary Round Question 10

BBB · BBB 2021 - Grade 3 - Preliminary Round

Question 10

To process 240 components, it requires 6 workers to finish within 8 days. Now the coordinators need to finish the job earlier. They add 4 workers to help. How many days are required to finish this set of components?
  1. 5
  2. 4
  3. 6
  4. 7