TIMO 2021 Grade 5 Preliminary Set 4 Question 4

TIMO · TIMO 2021 Grade 5 Preliminary Set 4

Question 4

Alice needs 60 days to finish a project. Peter needs 15 days to finish the same project. If Alice and Peter do the project together, how many days do they need to finish it?

Question illustration
  1. 75
  2. 12
  3. 45
  4. 20